Holiday Inn liked our sample room a lot, so now we are busy starting the process to make sure that every room in the hotel meets the same high standards - with one or two tweaks!
We have fought through the almost daily showers to complete the roof at last, and have e
Along with pushing on with the project, this week we have had a special job... finishing one of the rooms so that it can be inspected and approved by Holiday Inn.
This means that in the middle of a building site full of half completed hotel rooms - with all thei
It looks like we had overnight visitors who left their calling card in the field opposite the Hotel.
Usually on a project of this size progress seems to slow right down once the roof of the building is on – everything happens inside the building shell and different tradesmen have to take turn at working in the building. As you can see, there is
With the last of the big lifts completed when the roof structure of the north wing was finished, the crane has been used to distribute new material for internal finishes around the site and remove the material left over from the construction of the shell of the building.
Last weekend our electricity supplier connected up our new transformer to the high voltage supply, so at last we are ‘on the mains’ and have said goodbye to the generators that have powered the site until now.
We’ve also installed the underground ga
Work on the Hotel during the last two weeks has meant dodging in and out of the showers, but we’re keeping on schedule with construction.
The rain has tested the temporary roof on the south guest room wing and the building there has dried out so fast that
Progress in the good weather from last Monday has given us a whole first floor of bedrooms on the north wing – our fastest build with the timber frame to-date!
We also completed the roof deck and installed temporary sheet weathering to the south wing just in time for the rain to start today.
All of the timber panels which were delivered to site in the last two weeks are now in place and form the ground floor north wing hotel rooms - last Friday the site was starting to look empty again.
However the end of th
09 Jul 10
28 Jun 10
26 May 10
12 Apr 10
29 Mar 10
29 Mar 10
22 Mar 10
18 Mar 10
17 Mar 10
09 Mar 10
22 Jan 10
05 Jan 10
15 Dec 09
10 Dec 09
14 Oct 09