The longest spell of continuous dry weather (now more than two weeks without any rain at all) has enabled us to make rapid progress to the building elevations and roof, and so the appearance of the Hotel, albeit screened still by the scaffolding to the main elevations – is now becoming apparent. Wait until next week – the scaffolding will be almost gone!
Inside, lower ground floor hotel rooms are getting finished, and the last of the fixtures and fittings are being delivered ready to complete them ready for furnishing so that they can be filled with our guests as soon as we are open.
The Hotel kitchens are also taking shape, and the grand entrance to the hotel will soon be finished, the large windows which look out to the main entrance glazed so that we can start finishing the huge reception hall inside the building.





Categories: Construction, Weather, September, Rooms
09 Jul 10
28 Jun 10
26 May 10
12 Apr 10
29 Mar 10
29 Mar 10
22 Mar 10
18 Mar 10
17 Mar 10
09 Mar 10
22 Jan 10
05 Jan 10
15 Dec 09
10 Dec 09
14 Oct 09